Latest Project Updates
Rs.1356 Million New Electricity Transmission Project in Jhalawar, Rajasthan
Executive Summary: A new electricity transmission project in Jhalawar, Rajasthan, aims to build a 220/132 kV substation with a 1X160 MVA transformer at Hemda to enhance power reliability. Estimated at Rs. 1,356 million, it is planned from August 2025 to July 2027 and is currently in the DPR/Feasibility Study stage, to be executed via the EPC route.
Rs.1022 Million New Power Transmission Project in Jaisalmer, Rajasthan
Executive Summary: A new power transmission project is planned in Betina, Jaisalmer, involving a 220/132 kV and 132/33 kV grid substation to boost electricity reliability in Betina, Dangri, Sankra, and nearby areas. Estimated at Rs.1022 million, construction is set from July 2025 to March 2027 and is currently in the DPR/Feasibility Study stage under the EPC route.
Rs.5500 Million Fertilisers Mfg. Expansion Project in Kota, Rajasthan
Executive Summary: A new ammonium nitrate plant is being developed in Gadepan, Rajasthan, with ₹16,450 million invested to produce 220,000 tpa of Technical Ammonium Nitrate and 180,000 tpa of weak nitric acid. Expansion clearance was granted in May 2024. Further upgrades will increase ammonia, urea, and power capacities by 2027, with construction from 2026 to 2029.
New Clinker Grinding Unit in Ganganagar, Rajasthan
Executive Summary: A new clinker grinding unit is planned in Thukrana and Prabhat Nagar, Suratgarh, Sri Ganganagar, Rajasthan, with a cement production capacity of 6.0 million TPA and a 630 KVA DG set. The project, costing Rs. 83.429 million, is scheduled from March to December 2026. As of August 2025, it is under environmental clearance review with additional details requested.
Rs.2070 Million New Multispeciality Hospital in Churu, Rajasthan
Executive Summary: A new multispeciality hospital is planned in Sujangarh, Churu, Rajasthan, including residential and allied facilities. Estimated at ₹2,070 million, the project covers comprehensive civil, electrical, and mechanical works to establish a modern healthcare center. As of July 2025, bids have been invited for construction, aiming to enhance medical infrastructure and services in the region.
Rs.1661 Million New Poly Viscose (PV) Spun Yarn Mfg. Project in Bhilwara, Rajasthan
Executive Summary: A new Poly Viscose (PV) spun yarn manufacturing project is underway in Bhilwara, Rajasthan, with a total capacity of 35,904 spindles and an estimated cost of ₹1,661 million. Phase I is set to begin operations in July 2025, followed by Phase II in October 2025. As of July 2025, the project is under implementation.
Rs.1448 Million New Industrial Shed for Fabric Processing Unit in Bhilwara, Rajasthan
Executive Summary: A new industrial shed project for a fabric processing unit is proposed in Mandapiya, Bhilwara, Rajasthan. Aimed at supporting textile operations like dyeing and finishing, the project is estimated to cost ₹1,448.51 million. As of July 2025, the proposal has been submitted to the State Level Environment Impact Assessment Authority for environmental clearance and is currently under review.
Rs.30760 Million New Integrated Cement Plant in Jaisalmer, Rajasthan
Executive Summary: A new integrated cement plant is proposed in Sonu village, Ramgarh Tehsil, Jaisalmer, Rajasthan, with 2.4 MTPA clinker and 4.0 MTPA cement capacity. The project includes a 20 MW CPP, 15 MW WHRS, 1,560 TPD synthetic gypsum unit, DG sets, and railway siding. Estimated at ₹30,760 million, construction is planned from June 2026 to May 2028, pending environmental clearance.
New Bulk Drugs-API Mfg. Plant in Chittaurgarh, Rajasthan
Executive Summary: A new bulk drugs and API manufacturing plant is planned in the RIICO Industrial Area, Soniyana, Chittaurgarh, Rajasthan, with an estimated investment of ₹50 million. Construction is scheduled to begin in January 2026 and conclude by May 2027. As of July 2025, the project has been submitted to the State Level Environment Impact Assessment Authority for environmental clearance.
Rs.72392 Million New Kadambari Pumped Storage Project in Rajasthan
Executive Summary: A 1,560 MW off-stream, closed-loop pumped storage project is planned in Pali and Sirohi districts, Rajasthan, involving construction of two new reservoirs. With an estimated cost of ₹72,392.1 million, construction is scheduled from April 2027 to September 2031. As of July 2025, the project has been accepted by the Ministry of Environment and referred to the Expert Appraisal Committee.