Copper Wire Drawing Expansion Project in Madchal Malkajgiri, Telangana
Executive Summary: A Copper Wire Drawing Expansion Project in IE Medchal, Telangana, aims to increase production capacity from 19.99 TPM to 199 TPM to meet rising market demand. As of June 2024, the project has received state pollution control consent, emphasizing compliance with environmental regulations. This expansion underscores efforts to boost local manufacturing capabilities, supporting economic growth and employment opportunities in the region.
Rs.520 Million New Building Construction Project in Mancherial, Telangana
Executive Summary: A new building construction project in Devapur, Mancherial, Telangana, involves constructing multiple blocks with S+5 floors, costing Rs. 520 million. As of June 2024, the project has received approval from state pollution control authorities, signaling adherence to environmental standards while aiming to meet local infrastructure demands and support regional development.
New Clinical Research Activity in Sangareddy, Telangana
Executive Summary: A new clinical research facility with 100 beds is planned in Medical Device Park, Sultanpur, Ameenpur, Sangareddy, Telangana, costing Rs. 14.6 million. As of June 2024, state pollution control authorities have granted approval for the project, signaling its advancement in enhancing medical research capabilities in the region.
Tablets, Capsules Mfg. Expansion Project in Sangareddy, Telangana
Executive Summary: A manufacturing expansion project in IDA Bollaram, Jinnaram, Sangareddy, Telangana, involves increasing tablet production to 8 Lakhs Nos/Day, capsules to 1 Lakhs Nos/Day, and pellets to 100 TPM, costing Rs. 35 million. As of June 2024, the company has secured approval from state pollution control authorities to proceed, aiming to meet rising demand and enhance pharmaceutical production capabilities.
Rs.135 Million New Brake Components Mfg. Project in Rangareddy, Telangana
Executive Summary: A new project in Fab City, Raviryala, Maheshwaram, Rangareddy, Telangana, involves manufacturing precision engineering structural and brake components with a capacity of 40 TPM, costing Rs. 135 million. As of June 2024, the company has obtained approval from state pollution control authorities to proceed, emphasizing its commitment to expanding manufacturing capabilities in compliance with environmental standards.
Rs.176 Million New Rerolling Mill in Sangareddy, Telangana
Executive Summary: A new rerolling mill is planned in Bolarum, Telangana, with a capacity of 72,000 TPA to produce MS rods (8mm, 10mm, 12mm). The estimated cost is Rs. 176.6 million. Construction activities are scheduled to begin in July 2023 and end in the same year. Environmental clearance for the project is underway as of June 2023.
Rs.1500 Million New ESI Hospital Project in Shamshabad, Telangana
Executive Summary: A 100-bed ESI Hospital project in Shamshabad, Telangana, is planned with an estimated cost of Rs. 1500 million. Construction starts in May 2025, ending by April 2027. As of June 2024, the project is in the Idea Stage, utilizing the Engineering, Procurement, and Construction (EPC) route. It highlights ESIC's dedication to improving healthcare infrastructure and providing accessible medical services in the region.
Induction Furnace Expansion Project in Ranga Reddy, Telangana
Executive Summary: A company plans to expand its induction furnace project in Mahaboobnagar, Telangana, adding one more furnace to increase ingot/billet production to 1200 TPD. The project is estimated to cost Rs.50 million, with a total capacity of 30,000 TPA for MS Ingots and Billets and 270,000 TPA for MS TMT bars. The company is awaiting environment clearance as of February 2023.furnace in the same premises. After expansion the total production capacity of ingots/billets will be 1200 TPD.
Rs.7000 Million New Greenfield Facility in Telangana
Executive Summary: A new Greenfield Facility in Telangana's Peddapalli marks a strategic expansion for a beverage giant, representing its third such facility for fast-moving cool drinks. With a Rs. 7000 million investment, the project aims to meet market demand, foster regional growth, and enhance operational presence. It promises economic benefits for Peddapalli and bolsters Telangana's industrial development.
Rs.274 Million Seeds Processing Expansion Project in Medchal-Malkajgiri, Telangana
Executive Summary: A seeds processing expansion project is planned in Kandlakoya, Medchal-Malkajgiri, Telangana, to increase capacity by 2.9 TPD. The project, costing Rs. 274.628 million, aims to meet rising agricultural demands. As of June 2024, it has received approval from state pollution control authorities, ensuring environmental compliance and paving the way for enhanced infrastructure and technology.