New Steel and CR Strips Manufacturing Unit in Howrah, West Bengal
Executive Summary: A new Steel and Cold Rolled CR Strips Manufacturing Unit is planned in Howrah, West Bengal, with a production capacity of up to 500 metric tonnes per month and an estimated cost of ₹46 million. As of October 2024, the project has received Consent to Establish from the West Bengal Pollution Control Board, marking progress in its development.
Rs.10000 Million Integrated Steel Plant Expansion Project in Paschim Medinipur, West Bengal
Executive Summary: An integrated steel plant expansion in Gokulpur, Paschim Medinipur, West Bengal, will increase production capacity from 2.0 to 4.2 million tons per annum (MTPA) of finished steel and establish a 536 MW captive power plant. The project, involving an investment of ₹10,000 million, is set for construction from July 2024 to June 2031, having received state pollution control consent.
Rs.90 Million New Cycles Mfg. Project in Kharagpur, West Benga
Executive Summary: A prominent bicycle manufacturer plans to expand with a new facility in Vidyasagar Industrial Park, West Bengal, focusing on producing 500 cycles per day. The project, with an estimated investment of Rs. 90 million, aims to enhance production efficiency, incorporate advanced technology, and promote eco-friendly transportation. Pre-project activities, including site preparation, are underway as of October 2024.
New Elastic Tapes Mfg. Project in Howrah, West Bengal
Executive Summary: A new elastic tapes manufacturing project is planned in South Sankrail, Howrah, West Bengal, with an annual production capacity of 5 million meters. The project, estimated to cost ₹43.5 million, has received consent from the state pollution control authorities as of October 2024. It aims to contribute to the local economy and create job opportunities.
New Bio Diesel Mfg. Project in Purba Midnapur, West Bengal
Executive Summary: A new edible vegetable oil manufacturing project is underway in Debhog, Purba Midnapur, West Bengal, with a capacity of 700,000 metric tons. The expanded scope includes producing biodiesel, fatty matter, and crude glycerine. The project also involves processing Esterified Oil and Non-Edible grade Oil, with a capacity of 30,000 MT/M, and a total investment of ₹1.21 billion.
Rs.5380 Million New Ferrous & Non Ferrous Expansion Project in Bankura , West Bengal
Executive Summary: A major steel plant expansion is planned in Bankura, West Bengal, involving new DRI and iron ore beneficiation plants, rolling mills, induction furnaces, ferroalloy units, and a 45 MW captive power plant. The project will boost production of iron ore concentrate, pellets, and steel products, with an investment of Rs. 5,380 million. Environmental clearance was secured by October 2024.
Rs.147 Million New Lead Acid Battery Mfg. Unit in Hooghly, West Bengal
Executive Summary: A new lead-acid battery manufacturing unit is planned in Gopalpur, Majinan, P.S. Gurap, Hooghly, West Bengal, aimed at meeting rising demand in various sectors. The project will utilize modern manufacturing technologies to ensure efficiency and environmental compliance. As of October 2024, the company has obtained consent from state pollution control authorities to proceed with the establishment.
Rs.11336 Million New Raghunathpur Thermal Power Station Phase-II in Purulia, West Bengal
Executive Summary: A new thermal power station is being developed in Purulia, West Bengal, with two units of 660 MW each. The project, costing Rs. 11,336 million, is scheduled to start construction in December 2023 and complete by August 2028. As of October 2024, the project is at the tender publication stage and is progressing through the EPC route.
Rs.6680 Million Steel Plant Expansion Project in Bardhaman, West Bengal
Executive Summary: A steel plant expansion is planned in Raturia Industrial Area, West Bengal, involving upgrades to existing units and new facilities to produce 0.197 MTPA liquid steel, 0.355 MTPA hot metal, and 30,000 TPA slag cement. The Rs. 6,680 million project is set to begin construction in December 2024, with environmental clearance currently under review by the Ministry of Environment.
Rs.65000 Million Gas Exploration Project in Paschim Bardhaman, West Bengal
Executive Summary: A major coal bed methane (CBM) extraction project is set to launch in Damra, Raniganj CBM Block, West Bengal, with an investment of Rs. 65,000 million. The project aims to tap into local methane reserves, contributing to cleaner energy solutions. Construction will begin and conclude in November 2024, pending environmental clearance from the State Level Environment Impact Assessment Authority.